Demand Connections Update: What the New Queue Entry Requirements Mean for Large Energy Users 

New Demand Connection Requirements Start From 1 June 2026 

From 1 June 2026, new minimum information requirements will apply to electricity demand connection applications at 5MVA and above across Great Britain. 

The changes apply to: 

  • New demand connections at 5MVA or above  
  • Existing sites increasing demand capacity to 5MVA or above  

The reforms are part of wider UK Connections Reform led by Ofgem, the ENANational Energy System Operator (NESO), and network operators in response to growing demand for grid capacity. 

For developers and large energy users, the new requirements are designed to improve queue quality, prioritise viable projects, and support a faster, more efficient connections process over time. 

In this article, we look at what’s changing, who’s affected, and what projects should be doing now to prepare. 

 

Why Are the Rules Changing? 

The UK electricity network is seeing significant growth in demand connection applications across sectors including: 

  • Hydrogen production  
  • Heat networks and large-scale heating projects  

 

At the same time, network operators are managing increasing pressure on existing connection queues. 

The reforms aim to address growing backlogs, improve queue management, and ensure projects entering the system are progressing with genuine intent and realistic delivery plans. 

The changes form part of the wider “Curate, Connect and Plan” approach to UK Connections Reform, which aims to: 

  • Curate – remove stalled or speculative projects from queues  
  • Connect – prioritise projects that are ready to progress  
  • Plan – improve long-term network planning and coordination  

Together, these reforms are intended to support faster, more transparent, and more deliverable electricity connections across the UK. 

What Are the New Queue Entry Requirements? 

From 1 June 2026, applicants for demand connections at 5MVA and above will need to provide additional supporting information as part of their application. 

The requirements closely mirror the generation queue entry reforms introduced last year for projects above 1MVA. 

Letter of Authority (LoA) 

Applicants must provide a Letter of Authority confirming permission to act on behalf of the customer or landowner. 

LoAs can cover multiple sites where the parties remain the same. 

Heads of Terms (HoTs) 

Signed Heads of Terms will be required to demonstrate land rights and project progression. 

These must be: 

  • Site-specific  
  • Landowner-specific  
  • Signed by solicitors  

 

This helps demonstrate that projects are progressing beyond early-stage feasibility. 

Single Line Diagram (SLD) 

A Single Line Diagram (SLD) will be required where equipment could create voltage or harmonic impacts on the network. 

Typically, this should include: 

  • Point of Supply (PoS)  
  • Main switchgear  
  • Transformers  
  • Major load equipment  

 

Preliminary Project Timeline 

Applicants must also provide an indicative project timeline showing expected delivery milestones and progression. 

 

What Does This Mean for Demand Customers? 

The main change is that projects will need to be more developed before entering the connections queue. 

Applicants will increasingly need to demonstrate: 

  • Site control and land rights  
  • Project maturity  
  • Technical consideration  
  • A realistic delivery programme  

 

While this creates more upfront preparation, the long-term aim is a more efficient and streamlined process for projects that are genuinely ready to move forward. 

For large demand customers, early planning and engagement will become more important than ever. 

 

How Eclipse Power Can Help 

At Eclipse Power, our experts support developers, investors, utilities, and large energy users through every stage of the connections process. 

We help customers prepare robust, application-ready projects through services including: 

  • Demand connection strategy  
  • Grid feasibility studies and capacity assessments  
  • Technical documentation and SLD preparation  
  • Application support and programme planning  
  • DNO engagement  
  • Contestable and non-contestable works review and assessment
  • Ongoing support through Connections Reform changes  

 

Importantly, we also have in-house land rights expertise, helping customers navigate the increasing focus on land agreements as part of the reformed queue entry process. 

Whether you’re delivering a data centre, EV charging hub, industrial facility, or large commercial development, early engagement can help reduce delays and improve project readiness. 

As the industry moves toward a more evidence-based connections process, having the right technical and regulatory support in place will be key. 

 

Get in Touch 

If you’d like to discuss how the new demand connection requirements could affect your project, get in touch with our team – we’re here to help! 

Contact Us

Further Reading and Industry Guidance 

Share this page: